New Builds New Build 040

Week 33

Click on any of the images below to view in more detail.

Non-slip deck grating is now fitted behind the wheelhouse 

The main engine exhaust system showing two inlets to the silencer;one from each side of the engine 

Working on the engine room pipework 

The framing on the fish room ceiling has been completed 

Another part of the framing on the fish room ceiling 

The galley floor units have been completed 

Making connections to the gearbox 

The hydraulic pipework to the net drums has been fitted 

Painting inside the shelter deck 

The shower room under construction 

More electrical fitting being done in the wheelhouse 

The front of the wheelhouse where displays are to be mounted 

Panelling work continues in the wheelhouse