New Builds New Build 040

Week 29

Click on any of the images below to view in more detail.

Building wall framing in the accommodation access stairway 

Finishing off the handrails on the upper deck 

Cable trays are being fitted in the engine room 

The main engine and gearbox are now in place 

The port auxiliary engine is now in the engine room 

The two starboard auxiliary engine s have also been lifted into the engine room 

Paneling of the deck house is now well under way 

Electrical cables are now being run through the deck house 

The seating in the mess area is taking shape 

Decking and its supports are being fitted on parts of the upper deck, behind the wheelhouse 

The flooring has now all been laid in the wheelhouse 

Framing of the wheelhouse roof now looks to be complete 

Electrical cables are being run into the wheelhouse 

Paneling of the wheelhouse walls is progressing well