New Builds New Build 040

Week 26

Click on any of the images below to view in more detail.

Progress in the accommodation section 

Hand rails have been fitted on the starboard side of the upper deck 

Hand rails are being built around the bow 

Working on the hand rails 

Bases have been built for the galley units 

Seating is progressing in the mess 

Ceiling framing is being built for the mess and galley area 

Fitting a porthole in the galley area 

The hatch between wheelhouse and deck house has been fitted